Roof Demolition Completed!

As the month of June comes to an end, the final demolition of the roof at the Shrine has been completed!! Debris has been cleared and work continues to further the progress of the Shrine’s restoration.

Meanwhile, Wiss Janney Elstner (WJE) is in the office creating drawings and structural steel details for the construction of the new roof. Their drawings are due on July 19, 2016.

Also at this time, Simpson, Grumertz & Heger (SGH) are compiling all the data they gathered from their exterior survey and are creating documents that are due on July 29, 2016.