Roof Decking during Phase 1 Continues

CHICAGO, IL – This week at the Shrine, the roof decking continues…

– Decking on the north wall at the altar. Note the new bricking to the top of the column.

– Note two more completed columns on the south wall. Final roof support steel work here to be finished today. All steel work and decking to be finished this week!

– Decking to be completed between trusses 4 & 6 (right and left sides of the photo below) in the next two days. Field weld inspections and report are pending.

– Southwest corner masonry will be finished this week.

– Awaiting roofer availability to install underlayer and shingles!